Pile groups in under-reamed pile foundation can be tested by means of _________
Free standing piles and Pile foundation
Cannot be tested
None of the mentioned
All of the mentioned
Explanation:
Pile groups may be tested as both free standing piles or piled foundation by applying series of load.
Question 2
Marks : +2 | -2
Pass Ratio : 20%
In the process of pile foundation, boring is done with the help of _________
Boring guide
Under-reamer
Spiral auger
Pile beams
Explanation:
Boring is done with the help of spiral auger, present at the circular collar of the guide assembly.
Question 3
Marks : +2 | -2
Pass Ratio : 20%
The dimension of the bulb in an under-reamed pile can be checked by __________
Meter scale
G.I pipe assembly
Auger
Under-reamer
Explanation:
The dimensions of the bulb can be checked by means of a graduated G.I. pipe assembly.
Question 4
Marks : +2 | -2
Pass Ratio : 20%
The equipment required for construction of a under-reamed pile is________
Auger boring guide
Spiral auger
Concreting funnel
All of the mentioned
Explanation:
The equipment required for the construction of pile are i) Auger boring guide ii) spiral auger with extension rods iii) under-reamer with soil bucket and iv) concreting funnel.
Question 5
Marks : +2 | -2
Pass Ratio : 20%
Routine tests are usually carried out on _________
Test piles
Working piles
None of the mentioned
All of the mentioned
Explanation:
Routine test should be carried out on test piles while initial test are preferably carried on test piles.
Question 6
Marks : +2 | -2
Pass Ratio : 20%
For completion of one under-ream, how many buckets of earth are required for removal?
Five
Ten
Eight
Three
Explanation:
Generally, removal of eight buckets full of earth is required for completion of one under-ream.
Question 7
Marks : +2 | -2
Pass Ratio : 20%
The depth of the bore hole is checked at _________ before insertion of the under-reamer.
At the start and At the end
Each time
None of the mentioned
All of the mentioned
Explanation:
The depth of the bore hole is checked each time before insertion of the under-reamer so that any loose earth spilled from the bucket is removed.
Question 8
Marks : +2 | -2
Pass Ratio : 20%
Which of the following stages are involved in the construction of under reamed piles?
Concreting of piles and Boring by auger
Concreting the funnel
None of the mentioned
All of the mentioned
Explanation:
The various stage involved in the construction of under reamed pile foundation are i) boring by auger ii) under-reaming by under-reamer iii) placing reinforcement cage in position iv) concreting of pile caps, plinth beams and curtain walls.
Question 9
Marks : +2 | -2
Pass Ratio : 60%
The use of bore guide in under-reamed pile foundation is essential for __________
To drill the bore hole
To provide a support to the pile
To keep the bore holes vertical
To set the guide assembly in position
Explanation:
The used of boring guide is essential in order to keep the bore holes vertical and also in its position.
Question 10
Marks : +2 | -2
Pass Ratio : 20%
Enlarging the stem of bore hole at the depth is done by using________
Spiral auger
Under-reamer
Boring guide
None of the mentioned
Explanation:
Under-reaming or enlarging the stem of bore hole at the required depths is achieved by means of the under-reamer consisting of a set of two collapsible blade assembly.