Types of Software Metrics

Question 1
Marks : +2 | -2
Pass Ratio : 100%
A graphical technique for finding if changes and variation in metrics data are meaningful is known as
DRE (Defect Removal Efficiency)
Function points analysis
Control Chart
All of the mentioned
Explanation:
Others options are formulas.
Question 2
Marks : +2 | -2
Pass Ratio : 100%
Which of the following is an indirect measure of product?
Quality
Complexity
Reliability
All of the Mentioned
Explanation:
All the mentioned options are indirect measures of a product.
Question 3
Marks : +2 | -2
Pass Ratio : 100%
Which of the following is not a direct measure of SE process?
Efficiency
Cost
Effort Applied
All of the mentioned
Explanation:
Efficiency is an indirect measure.
Question 4
Marks : +2 | -2
Pass Ratio : 100%
Which of the following does not affect the software quality and organizational performance?
Market
Product
Technology
People
Explanation:
Market is a collection of competitors, stakeholders, users each having different views on the product. So it does not affect the software quality.
Question 5
Marks : +2 | -2
Pass Ratio : 100%
The intent of project metrics is:
minimization of development schedule
for strategic purposes
assessing project quality on ongoing basis
minimization of development schedule and assessing project quality on ongoing basis
Explanation:
A project metric is a quantitative measure of the degree to which a system, component or process possesses an attribute.
Question 6
Marks : +2 | -2
Pass Ratio : 100%
Defects removal efficiency (DRE)depends on:
E – errors found before software delivery
D – defects found after delivery to user
Both E and D
Varies with project
Explanation:
DRE = E / (E + d).
Question 7
Marks : +2 | -2
Pass Ratio : 100%
In size oriented metrics, metrics are developed based on the ___________________
number of Functions
number of user inputs
number of lines of code
amount of memory usage
Explanation:
None.
Question 8
Marks : +2 | -2
Pass Ratio : 100%
Which of the following is not an information domain required for determining function point in FPA ?
Number of user Input
Number of user Inquiries
Number of external Interfaces
Number of errors
Explanation:
FPA includes five domains namely input, output, inquiries, interface and logical files.
Question 9
Marks : +2 | -2
Pass Ratio : 100%
Which of the following is the task of project indicators:
help in assessment of status of ongoing project
track potential risk
help in assessment of status of ongoing project & track potential risk
none of the mentioned
Explanation:
None.
Question 10
Marks : +2 | -2
Pass Ratio : 100%
Usability can be measured in terms of:
Intellectual skill to learn the system
Time required to become moderately efficient in system usage
Net increase in productivity
All of the mentioned
Explanation:
None.